What can a client recover under IChemE Red Book?

As my introductory post on IChemE sets out, there are some significant limits under the Red Book on the rights of the purchaser to recover losses. What can you do about it? This post considers the purchaser’s remedies. Remedies As the purchaser – either yourself or through the project manager

Read More »

Limits on the contractor’s liability under MF/1

MF/1 is a balanced contract providing plenty of opportunities for the purchaser to check the performance of the works – through three series of tests – before the contractor is released from liability.  It also clearly sets out limits on the contractor’s obligations. Limits on scope If you are acting

Read More »

What can a client recover under MF/1?

As my introductory blog on MF/1 sets out, there are some significant limits under MF/1 on the rights of the purchaser (client or employer) to recover losses. What can you do about it? This blog considers the purchaser’s remedies. Remedies As the purchaser, you – either yourself or through the

Read More »

Role of the Engineer under MF/1

The Engineer’s role under MF/1 (like any contract administrator) is a balancing act. Firstly, they are an agent for the purchaser, as well as an employee. The engineer issues ‘certificates, decisions, instructions and orders’ (clause 2.1) but only as set out in the contract. The engineer’s authority derives from the

Read More »

Contracts create disputes

The Global Construction Disputes Report 2019 (by Arcadis) confirms that failure to understand or comply with the contract is the number one cause of disputes globally. Professor Renato Nazzini, in his guest foreword says: It would be tempting to look for solutions in ever more complex, more detailed contractual documents

Read More »

Culture change for BIM

The Cultural Impact of Implementing Building Information Modelling (BIM) in the UK Construction Industry (Andrew Johnson) confirms that using BIM requires a fundamental change in working style, which is a massive cultural shift from an adversarial culture to a collaborative culture. BIM requires all project partners to: collaborate, share data,

Read More »

Beware time-bar provisions

Adjudication is sometimes described as a rough and ready from of speedy dispute resolution and is mandatory for certain construction contracts in the UK. Where it is mandatory it can be commenced at any time. Where the contract does not come within the mandatory statutory requirements, eg for a residential

Read More »

Can you recover delay damages after termination?

Construction contracts and engineering contracts take a flexible approach to completion: time is not of the essence (if they were, then when the contractor was late the client could reject the works, plant or section and pay nothing) the original dates for completion of the work, plant or sections can

Read More »

Fitness for purpose under MF/1

Fitness for purpose clauses impose a duty on a contractor to achieve a specific result. They have come under scrutiny as a result of a series of cases in the English courts which imposed significant damages onto a contractor, in complex factual scenarios [read more]. This post considers the MF/1

Read More »

Fitness for purpose under FIDIC contracts

Fitness for purpose clauses impose a duty on a contractor to achieve a specific result. They have come under scrutiny as a result of a series of cases in the English courts which imposed significant damages onto a contractor, in complex factual scenarios [read more]. This post considers the FIDIC

Read More »